New and dark pavement shows pathway for large PVC pipes that will replace the “ditch” and syphon at Gallagher Lake. Project expected to be totally ready for the 2022 irrigation season.
Below work continues between Hwy 97 and Frontage Rd – southward until the 2nd crossing can be dealt with near James Way – the white pipes reconnect with the 100 year old “ditch” on OIB land.