Fairview Road – Kootenay to Gala Streets – as well Spartan Street sidewalk improvements
UPGRADES AND NEW INSTALLATIONS OF SIDEWALK, STORM AND ROAD INFRASTRUCTURE
The Town of Oliver has awarded the project to reconstruct, upgrade and pave a portion of Fairview Road between Main Street and Nicola Street to Mike Johnson Excavating Ltd. The project includes constructing a new sidewalk, curb and storm on Spartan Street between Fairview Road and Rockcliffe Road.
There will be times that residents and businesses will not have vehicular access to their property from Fairview Road due to temporary shut downs, but back alley access behind the properties will still be available at all times.
During most of the project there will be access to businesses on the north side of Fairview Road; the west bound lane will be open with access to parking stalls. Mike Johnson Excavating Ltd. will do their best to notify businesses and residents in advance and to keep these interruptions as short as possible. The south side properties of Fairview Road will be affected the most during construction, but will have back alley access for the duration of the project.
Schedule of Construction (please note the schedule is approximate):
June 20
Mobilization and site preparation including asphalt
June 20 -July 8
Installation of underground works including
July 11-July 22
Site preparation and storm sewer for Spartan St.
July 25 -August 5
Excavation and sub-base gravels
August 8 -12
Concrete curb & gutter
August 15- 19
Concrete sidewalk
August 22 -26
Asphalt paving
August 29 – September 2
Site clean-up and demobilization.
The Spartan Street portion of the project will not affect residences on the west side except that part of the road on the east side will be under construction and the road may be portioned off to allow this work to be done. We urge people to take precautions through the construction areas and apologize for any inconveniences this may cause.