Construction on the Satikw Crossing bridge across the Okanagan River Channel reached a milestone this week as the last of the 36 concrete girders were installed.
“We’re across the channel and are about halfway to completion,” said Penticton Indian Band Chief Jonathan Kruger. “To see the bridge taking shape is a big inspiration for everyone. It’s a 20-year dream finally taking true form in steel and concrete.”
The next phase will see the bridge deck concrete work and Highway 97 road construction to enable opening of two lanes northbound and southbound before the end of June.
About the same time, the Green Avenue intersection will be closed to traffic. Detours will be in effect until October. During the summer, work will continue on the bridge and at the Green Avenue intersection.
Coyote Cruises will be fully operational as usual for the summer tourist season.